Eliwana RC50
Eliwana RC50

Case study

Eliwana RC50

Late 2019, Ausco Modular’s Remote Accommodation team successfully mobilised a 304-person camp to site at the Eliwana Mine and Rail project in the Pilbara, Western Australia.

 

Fast Facts

 

Client

Fortescue Metals Group

 

Location

Pilbara, WA

 

Time to install

Handover within 5 weeks

 

Solutions

304-person mobile camp


Fortescue Metals Group’s US$1.375 billion project included the development of 143 kilometres of rail, a 30 million tonnes per annum dry ore processing facility and infrastructure, with first ore on train delivered in December 2020.

The mobile camp was installed to accommodate Fortescue’s workforce during the construction of the railway.